• Home
  • Our Project
  • Progress
    • General Building
    • External Works
    • Kitchen
  • Sign Up!

Recent Posts

  • Finally – a photo finish…!
  • Week 69 – One more week to handle
  • Week 68 – Skipping ahead
  • Week 67 – Edging ever closer
  • Week 66 – Cracking on after a short break

Previous Months

  • May 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021

Categories

  • Bathroom
  • En Suite
  • External Works
  • General Building
  • Hall & Entrance
  • Kitchen
  • Stairs & Landing
Skip to content
House renovation
  • Home
  • Our Project
  • Progress
    • General Building
    • External Works
    • Kitchen
  • Sign Up!

Month: May 2022

Week 29 – Painting, Plastering & Prep

by JamesExternal Works, Hall & Entrance, Kitchen, Stairs & LandingPosted on May 29, 2022Comments are Disabled

Painting of kitchen, plenty of plastering and rendering and preparation of hall & landing

Week 28 – The Wood Works work

by JamesHall & Entrance, Kitchen, Stairs & LandingPosted on May 22, 2022May 22, 2022Comments are Disabled

Kitchen in (phase 1) and lots of stripping and preparation work across the house

Week 27 – Happy feet

by JamesKitchenPosted on May 15, 2022May 15, 2022Comments are Disabled

Internal tiling & essential painting completed – ready for the kitchen fit!

Week 26 – A weekend of getting plastered

by JamesKitchenPosted on May 9, 2022May 9, 2022Comments are Disabled

Floor screed in, plaster-boarding and plastering completed

Week 25 – A positive week!

by JamesKitchenPosted on May 1, 2022May 1, 2022Comments are Disabled

Tunnel gone. last wall down and onto plaster boarding and floor prep