Finally – a photo finish…!
A long overdue final post now the project is completed. Lots of pictures to give a final view of the work.
A long overdue final post now the project is completed. Lots of pictures to give a final view of the work.
Painting of patio walls and steps, fitting of patio balustrade frame and general clearing & tidying
Cracks re-painted throughout, patio door area tiled and drainage fitted and various other finishing tasks completed
Decking fully fitted, including side panels and edges and a few internal jobs ticked off the list
Main grouting finished, side steps formed and tiled and walls and stairs painted throughout
Coping edges completed, decking and grouting started.
Main patio areas completed, coping edging started and lots more groundwork and levelling and grading of beds and garden areas.
A week focussed on outside work, lot’s more progress on the patio, painting of external walls and more digging and bed preparation
Major focus on the outside work, with patio going back down and lots of digging and groundwork to beds. Further completion of snagging list internally.
External roof and pipework completed, lots of painting to kitchen ceiling & walls and multiple items of snag list completed – all before a great Christmas Day.