Week 69 – One more week to handle
Near completion of the internal work, with final
painting and sealant applied and multiple door handles and locks fitted
Near completion of the internal work, with final
painting and sealant applied and multiple door handles and locks fitted
Patio laid, and then removed! Great progress on the bathroom and lots more sorting and tidying throughout
External painting completed, scaffolding down, grouting finished and porch prepared.
Full steam ahead with main bathroom, lots more painting and initial guttering work
Chimney work, lots of internal & external painting and groundwork repairs mainly to lawn
Woodwork painted, door furniture fitted and first few bits of wallpapering hung
First carpet fitted, outside brickwork, bathroom ripped out and various carpentry work throughout
Tiling in hall & cloakroom, and lots more painting and decorating throughout
Scaffolding up, hall floor levelled and ensuite tiling started
Arch removed, final steel in and work started on the stairway – plus lots more decoration and new window work