Week 30 – Jubilee Week!
Short week, but still good progress in a number of rooms and areas
Short week, but still good progress in a number of rooms and areas
Painting of kitchen, plenty of plastering and rendering and preparation of hall & landing
Kitchen in (phase 1) and lots of stripping and preparation work across the house
Internal tiling & essential painting completed – ready for the kitchen fit!
Floor screed in, plaster-boarding and plastering completed
Tunnel gone. last wall down and onto plaster boarding and floor prep
Patio doors are in, and we are water tight again!
Plumbing, electrics and further roof work
Roof lanterns and window frame in, electrical work started
Roof in, up-stands built, windows & tiles delivered and office destroyed!