• Home
  • Our Project
  • Progress
    • General Building
    • External Works
    • Kitchen
  • Sign Up!

Recent Posts

  • Finally – a photo finish…!
  • Week 69 – One more week to handle
  • Week 68 – Skipping ahead
  • Week 67 – Edging ever closer
  • Week 66 – Cracking on after a short break

Previous Months

  • May 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021

Categories

  • Bathroom
  • En Suite
  • External Works
  • General Building
  • Hall & Entrance
  • Kitchen
  • Stairs & Landing
Skip to content
House renovation
  • Home
  • Our Project
  • Progress
    • General Building
    • External Works
    • Kitchen
  • Sign Up!

Progress

Week 20 – Bella & Bailey approved drainage

by JamesGeneral BuildingPosted on March 27, 2022March 27, 2022Comments are Disabled

Drainage & ceiling structure completed and extension roof underway

Week 19 – It’s all going to (open) plan

by JamesGeneral BuildingPosted on March 19, 2022March 19, 2022Comments are Disabled

Final steel in and kitchen fully opened up

Week 18 – Steel, one more to go

by ClareGeneral BuildingPosted on March 12, 2022March 12, 2022Comments are Disabled

Nearly there with the steels, and external rendering started

Week 17 – Reconstruction starts!

by JamesGeneral BuildingPosted on March 5, 2022March 5, 2022Comments are Disabled

Ceiling joists in as the extension starts to take shape

Week 16 – Tunnel vision

by ClareGeneral BuildingPosted on February 27, 2022March 5, 2022Comments are Disabled

Removal of bottom half of the chimney and more walls

Week 15 – Everything is still standing

by JamesGeneral BuildingPosted on February 20, 2022February 20, 2022Comments are Disabled

More steels and lots of storms

Week 14 – Remote kitchen…

by JamesKitchenPosted on February 12, 2022February 12, 2022Comments are Disabled

Temporary kitchen in place – all but a dishwasher…

Week 13 – Breakthrough!

by ClareGeneral BuildingPosted on February 5, 2022February 6, 2022Comments are Disabled

Kitchen windows and walls coming out quickly

Week 12 – Steeling ourselves for noise

by JamesExternal WorksPosted on January 29, 2022January 29, 2022Comments are Disabled

First steels now in place, focus moves to the house

Week 11 – Barrow loads of fun (!)

by ClareGeneral BuildingPosted on January 22, 2022January 23, 2022Comments are Disabled

External prep now looking good and nearing completion.